RTL delivers 785 tonnes of oversize equipment to Moscow oil refinery
RUSSIA-BASED project logistics provider RTL LLC has organised the delivery of four oversize cargoes - which had a combined weight of 785 tonnes - from Izhorskiye Zavody's plant in Kolpino, Leningradskaya region to the Moscow refinery owned by PJSC Gazprom Neft.
Initially, the units were transported from Izhorskiye Zavody's plant by heavy-duty vehicles to a pier built by RTL specialists on the River Neva, according to a company release.
The route was particularly challenging, passing through towns and over two railway crossings. To traverse the railways required the disconnection of high-voltage transmission lines and alterations to train schedules. Furthermore, RTL was responsible for strengthening the road surface to guarantee the safety of the consignment.
Upon arrival at the bespoke pier, the loading and securing of the cargoes onto a heavy-duty barge took two days to complete. The equipment was then shipped to Moscow via Russia's extensive inland waterway network, routing via the River Neva, the Ladoga Lake, Volga-Baltic canal, White Lake and the Sheksna River, Rybinsk reservoir, the Volga River and the Moscow Canal.
With the project coming close to completion, the final stage will see the four cargoes moved to their final installation site at the Moscow refinery.
In 2011 PJSC Gazprom Neft started a large project to modernise its Moscow refinery, removing outdated production facilities and introducing modern systems.
Initially, the units were transported from Izhorskiye Zavody's plant by heavy-duty vehicles to a pier built by RTL specialists on the River Neva, according to a company release.
The route was particularly challenging, passing through towns and over two railway crossings. To traverse the railways required the disconnection of high-voltage transmission lines and alterations to train schedules. Furthermore, RTL was responsible for strengthening the road surface to guarantee the safety of the consignment.
Upon arrival at the bespoke pier, the loading and securing of the cargoes onto a heavy-duty barge took two days to complete. The equipment was then shipped to Moscow via Russia's extensive inland waterway network, routing via the River Neva, the Ladoga Lake, Volga-Baltic canal, White Lake and the Sheksna River, Rybinsk reservoir, the Volga River and the Moscow Canal.
With the project coming close to completion, the final stage will see the four cargoes moved to their final installation site at the Moscow refinery.
In 2011 PJSC Gazprom Neft started a large project to modernise its Moscow refinery, removing outdated production facilities and introducing modern systems.
Latest News
- For the first time, tianjin Port realized the whole process of dock operati...
- From January to August, piracy incidents in Asia increased by 38%!The situa...
- Quasi-conference TSA closes as role redundant in mega merger world
- Singapore says TPP, born again as CPTPP, is now headed for adoption
- Antwerp posts 5th record year with boxes up 4.3pc to 10 million TEU
- Savannah lifts record 4 million TEU in '17 as it deepens port