Yangtze deepwater navigation channel rushed to completion in Nanjing
PHASE I of the Yangtze River 12.5-metre deepwater channel at Nanjing is expected to be done by July when dredging between Taicang to Nantong is complete, reports Xinhua.
The 12.5-metre deep channel project is an important infrastructure in Yangtze River to promote the region's water transport, logistics and social and economic development.
Construction of the deepwater channel was carried out in three phases with the first phase started in 2012. Investment in the project has reached CNY3 billion (US$48.3 million) as of now.
The phase 2 of the navigation channel has recently passed assessment by the state-owned CIECC Engineering Company Limited.
The 227-kilometre phase II starts from Xinshengyu port area in Nanjing to Tiansheng port area in Nantong, involving a total investment of about CNY7.98 billion (US$1.28 billion).
The 12.5-metre deep channel project is an important infrastructure in Yangtze River to promote the region's water transport, logistics and social and economic development.
Construction of the deepwater channel was carried out in three phases with the first phase started in 2012. Investment in the project has reached CNY3 billion (US$48.3 million) as of now.
The phase 2 of the navigation channel has recently passed assessment by the state-owned CIECC Engineering Company Limited.
The 227-kilometre phase II starts from Xinshengyu port area in Nanjing to Tiansheng port area in Nantong, involving a total investment of about CNY7.98 billion (US$1.28 billion).
Latest News
- For the first time, tianjin Port realized the whole process of dock operati...
- From January to August, piracy incidents in Asia increased by 38%!The situa...
- Quasi-conference TSA closes as role redundant in mega merger world
- Singapore says TPP, born again as CPTPP, is now headed for adoption
- Antwerp posts 5th record year with boxes up 4.3pc to 10 million TEU
- Savannah lifts record 4 million TEU in '17 as it deepens port